Wyreema Sewer and Water

CONNECTION OF WESTBROOK TO WYREEMA SEWER AND TOWN WATER

Newlands was contracted for design and construction of a water trunk main and construction of a sewer rising main and associated pump station. Works included a 4m dia. x 4m deep reinforced concrete wet well, tilt slab pump and control rooms, odour control systems, pipework interconnections and all electrical, mechanical and control works. Ancillary works included pavement construction and general earthworks.

Address Wyreema to Westbrook, Queensland
Client Toowoomba Regional Council
Sector Water and Sewer Reticulation
Services Engineering Design, Engineering Surveying, Utility Infrastructure and Plumbing
for:

  • 8.1km of 315OD PE100 SDR11 HDPE Rising Main
  • 6.9km of 200DN PN20 RRJ DICL Trunk Water Main
  • Cast-in-situ wet well (4.0m dia. x 4.0m deep)
  • Electrical Control Room (tilt-up construction)
  • Odour Control Building & MHL Injection System
  • Electrical and Control Systems
  • Asphalt Surfaced Flexible Pavement Construction
  • Reinforced Concrete Rigid Pavements
Key Personnel
  • Chris O’Dea
  • Grant Campbell
  • Michael Fogarty
Contract Value $6m
Project Length 11 Months