Carrington Road Trunk Sewer
Design and construct gravity sewer in Torrington
Newlands were engaged by Toowoomba Regional Council to design and construct gravity sewer mains to service the growing Torrington area.
Newlands constructed approximately 1.2 km of a combination of 375 mm diameter and 450mm diameter Ductile Iron Cement Lined Gravity Trunk Sewer Mains. The works included two aerial crossings over creeks, a portion of alignment within the Department of Transport and Main Roads boundary, and varied depths of 2 to 4m.
The overall duration of this project was 6 months.
Address | Carrington Road, Torrington |
Client | Toowoomba Regional Council |
Sector | Local Council |
Contract Value | >$3.1m |