ANZ Branch Toowoomba
Demolition of building, removal of asbestos, and construction of new building
This design and construct project consisted of the demolition of part of the existing building, the removal of asbestos materials, two levels of new building works to the rear of the original building and base building works to whole two levels of the final tenancy area.
The new structure to the rear of the building consisted of external fire rated block walls, block lift shaft, suspended timber flooring and timber truss and frame roof. New timber internal partitions, amenities, a lift and a new glazed shop front were also constructed as part of the scope.
Modification to the front and rear of the building were also made to allow compliant PWD access for the tenant.
This project was completed within a 5 month time frame.
Address | Ruthven Street, Toowoomba |
Client | Jillbridge Pty Ltd. |
Sector | Retail and Office |
Contract Value | $1m |