Project Highlights

Highfields Childcare

Bulk Earth works and Construction of 640m2 Childcare centre

Contracted works included bulk earthworks and retaining for the whole development, then the construction of a 640m2 childcare centre. Works also included construction of a shared driveway and carpark for the centre. Project difficulties included external sewer and stormwater works for the whole site and meeting particular construction requirements for childcare centres.

Address 73 Highfields Rd, Highfields
Client / Customer Civil Court Properties
Services
  • Road and Pavement Construction
  • Bulk and General Earthworks
  • Commercial Construction
Key Personnel
  • Bevan Austin
  • Michael Burchmann
  • Jason Kropp
Contract Value $1.5m - $2m
Contract Length 6 Months